Featured Road
Box Elder County, Utah
Project Profile
-
County:
Box Elder County
-
Road Length:
1 mile
-
Final Road State:
Full depth reclamation with chipseal top coat
-
Year Constructed:
June 2020
-
Traffic Profile:
Industrial and agricultural
-
Subgrade/Base Soil:
Clay
-
Equipment Used:
Reclaimer, water truck, motor grader, padfoot compactor, smooth wheel compactor

Challenge: Box Elder County needed a severe structural rehabilitation of a failing 1-mile paved corridor. Performing a traditional, high-cost dig-out or using rigid Portland Cement for stabilization were both pricey and labor intensive options. Instead, they performed a Full Depth Reclamation using Perma-Zyme to stabilize the reclaimed roadway material.
Results: By incorporating Perma-Zyme into the reclaimed pavement and native subgrade, Box Elder County created a stronger, more stable road base while improving compaction. This significantly reduced the total construction hours, offering immediate labor and equipment cost savings. After the subbase cured, a standard chipseal top coat was then applied directly to the Perma-Zyme stabilized road, delivering a long-term, high-durability paved surface at a fraction of the cost of traditional reconstruction.