Unpaved Road Sample Timeline

Day 1 – Shape road and drainage; and mix Perma-Zyme for 1 mile.

Day 2 – Lay out and compact first ½ mile.

Day 3 – Shape road and drainage and mix Perma-Zyme for second ½ mile.

Day 4 – Lay out and compact second ½ mile.

Day 5 – (24 hours) Allow full mile to dry.

Day 6 – (48 hours) Allow full mile to dry.

Day 7 – (72 hours) Allow full mile to dry.

Day 8 – Lightly cut (shave) and compact with steel wheel full mile.

Once compacted, the road may be used by light motor traffic, even if a top coat application is planned.